Question 768385: If x men working together at the same rate can complete a job in h hours, what part of the same job can one man working alone complete in k hours?
a. k/xh
b. h/xk
c. k/x+h
d. kh/h
e. kx/h

Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
Each man contributes his own part of the job rate so rates are additive. One man takes x times longer than x men.

x men__________________h hours for 1 job
1 man__________________h*x hours for 1 job


-----------
Having the one-man rate of job per hour you also can say the rate is hours per job.
If you want the man to do work for k hours, then:

job.

RELATED QUESTIONS

if x men working together at the same rate can complete a job in h hours, what part of... (answered by stanbon)
If x men working together can do a job in h hours, what part of the same job can one man... (answered by ankor@dixie-net.com)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)
If four men working at the same rate can do 2/3 of a job in 40 minutes, how many minutes... (answered by ankor@dixie-net.com)
If x people can work together at the same rate to complete a project in y hours, what... (answered by Okamiden)
One woman and one man can build a wall together in two hours, but the woman would need... (answered by josmiceli)
Joe can do a job in 6 hours and charlie can do the same job in 5 hours. What part of the... (answered by macston)
5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the... (answered by josmiceli)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)