Question 765124: 12 workers completed work in 40 days how many works required to complete work in 16 days
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
12 workers completed work in 40 days
----------------------------------
10 times as many workers can do the work in 1/10 of that time, or
120 workers can complete work in 4 days
------------------------------------
1/4 that many workers will take 4 times as long to complete work, or
30 workers can complete work in 16 days
-----------------------------------
You can also say that
( number of workers ) = k*( 1 / number of days to complete work )
( this is an inverse variation )



Now let = number of workers





RELATED QUESTIONS

An employer employees 28 men to complete a work in 30 days. 40% of work has been... (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
12 workers can do a piece of work in 16 days if 12 more workers are added in how many... (answered by Cromlix)
30 workers complete a work in 15 days and 36 workers to complete same work in how many... (answered by chibisan)
12 workers can do a piece of work in 20 days.How many workers should be added to complete (answered by richwmiller)
If 9 workers complete the work in 10 days how many workers will complete the same work in (answered by josgarithmetic,josmiceli)
A painting job can be completed by 3 painters in 17 days. If 12 more painters join the... (answered by josmiceli)
16 workers complete their work in 38 days. In how many days will it take if 5 of the... (answered by Theo)
12 men complete the 2400 square meter ploughing work in 10 days. how many men are... (answered by Alan3354)