SOLUTION: Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days 3 more men were added. How many days will it take to finish the job?
Algebra.Com
Question 765043: Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days 3 more men were added. How many days will it take to finish the job?
Found 2 solutions by ankor@dixie-net.com, josgarithmetic:
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
Twelve men can finish a job in 16 days.
Five men were working at the start, after 8 days 3 more men were added.
How many days will it take to finish the job?
:
Find the number of man-days required to do the job.
12 * 16 = 192 man-days
:
Let t = days worked after 8 days to complete the job
5(t+8) + 3t = 192
5t + 40 + 3t = 192
8t = 192 - 40
8t - 152
t = 152/8
t = 19 more days required to do the job
:
:
Check this: 5 men worked 19 + 8 = 27 days, 3 worked 19 days
5*27 + 3*19 = 192
Answer by josgarithmetic(39625) (Show Source): You can put this solution on YOUR website!
1. FIND WORK RATE FOR 1 MAN
12 men do the job in 16 days;
1 man does the job in 16*12 days, or
1 man's rate is jobs per day.
2. FORM WORK RATES FOR 5-MAN GROUP AND FOR 8-MAN GROUP
5-man work rate is simply and the 8-man rate is
3. SPLIT THE ANALYSIS INTO TWO TIME PHASES:
5 MEN FOR 8 DAYS,
AND
THE 8 MEN FOR SOME DAYS TO FINISH THE JOB.
The actual variable here now is for how many days were necessary to complete the job. The portions of job are added, or summed to be the whole job.
You do the rest of this.
RELATED QUESTIONS
twelve men can finish the job in 20 days. Five men were working at the start and after 10 (answered by lwsshak3)
Twenty men can finish the job in 30 days. Twenty five men were hired at the start and 10... (answered by josgarithmetic)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
Twenty men can finish the job in 20 days. Twenty men were hired at the start and 10 quit... (answered by richwmiller)
a piece of work can be done by 40 men in 48 days. after 15 days, 18 men were transferred... (answered by stanbon)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
A contractor estimates that he could finish a project in 15 days if he has 20 men. At the (answered by josmiceli)
a piece of work can be done by 40 men in 48 days, after 15days, 18 men were transferred... (answered by ankor@dixie-net.com)
10 men can do a piece of work in 24 days. After working 6 days,few men were added to... (answered by Edwin McCravy)