Question 751483: Two machines work together and complete work in 2 hours 24 minutes. If one machine works on its own it takes 2 hours longer than the other machine.How long does it take the slower machine to complete the work on its own?? Answer by stanbon(75887) (Show Source):
You can put this solution on YOUR website! Two machines work together and complete work in 2 hours 24 minutes. If one machine works on its own it takes 2 hours longer than the other machine.How long does it take the slower machine to complete the work on its own??
-----
Together rate: 1/144 job/min
Slower mach. rate: 1/(x+120) job/min
Faster mach. rate: 1/x job/min
-----
Equation:
rate + rate = together rate:
1/x + 1/(x+120) = 1/144
------
144(x+120) + 144x = x(x+120)
---
144x + 144*120 + 144x = x^2 + 120x
------
x^2 - 168x - 144*120 = 0
-------------------------
x = 240 minutes (time for the faster worker)
x+120 = 360 min (time for the slower worker)
============================
Cheers,
Stan H.
=============