Question 749943: It takes 1 work day to repair 100m of road. At this rate how many work days will it take to repair 20km of road?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
The rate is ( 100 m of road ) / ( 1 work day ) = ( in km/day )
( 20 km ) / ( km/day ) = days
It will take 200 days to rerpair 20 km of road
RELATED QUESTIONS
a company can repair 11/5 km of road in a day. How many days will it take to repair a... (answered by josgarithmetic)
It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if... (answered by lenny460)
it takes 8 workers to repair 750 yards of a road. how many days does it take 5 workers... (answered by Alan3354)
A crew repairs 1/12 mile of road each day, how long will it take the crew to repair a 3/4 (answered by rfer)
Two road crews, working together, repaired 1 mile of road in 4 hours. Working separately, (answered by checkley71)
two roads crew working together repaired 1 mile of the road in four hours. working... (answered by ankor@dixie-net.com)
It takes 4 men 6 hours to repair a road how long does it take 7 men?
(answered by edjones)
If 18 men can repair a road in 3 3/4 day in how many days can 15 men repair it
(answered by ikleyn)
It takes nine days for 8 worker to pave a stretch of road. If each worker works at the... (answered by Mathtut)