Question 745788: Peter and Paul can do a certaion job in 3 hours. On a given day, they worked together for 1 hour then Paul left and Peter finishes the rest of the work in 8 more hours. How long will it take Peter to do the job alone?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
If they can do the whole job in 3 hrs working
together, then in 1 hour, they can do
of the job
That means there is 2/3 of the job left to do
-----------------
Then, ( Peter's rate of working ) x ( 8 hrs ) = 2/3
Let = Peter's rate of working
Peter would take 12 hrs to do the job alone
check:
----------
Let = Paul's rate of working
In hr,
So, of the job is left
Peter does
OK
RELATED QUESTIONS
peter and paul can do a certain job in 3 hours. on a given day, they worked together for... (answered by ankor@dixie-net.com)
Peter and Paul can do a certain job in 3 hours. On a given day, they worked together for... (answered by stanbon)
Bea and Yan can do a certain job in 3 hours. On a given day, they worked together for 1... (answered by josmiceli)
Paul can do a certain job in half the time that Jim requires to do it. Jim worked alone... (answered by mananth,MathTherapy)
It takes Paul 4 hours to do a job. It takes Peter 2 hours to do that same job. How many... (answered by ankor@dixie-net.com)
there are 3 kids in a family . anna ,peter and maria .anna can clean the house fpor 1... (answered by josgarithmetic)
Paul can do a certain job in half the time that Jim requires to do it. Jim orked alone... (answered by josgarithmetic)
David earns $1.50 per hour more than Peter. Together they both work 40 hours in a week.... (answered by josgarithmetic)
Jane,Paul and Peter can finish painting the fence in 2 hours. If Jane does the job alone... (answered by scott8148)