Question 739967: : 5 man and 7 woman and 8 children can complete a work in 20 day and they work for 5 hours per day.how many days required to complete same work if 7 man 9 woman and 10 children work together they work for 7 hours ina day
Answer by KMST(5328)   (Show Source): You can put this solution on YOUR website!
INTERPRETATION:
If the only available information is that a group consisting of 5 men, 7 women and 8 children can complete the work in 20 days working 5 hours per day, the problem cannot be solved. There is not enough information. We do not know how fast the women can work compared to the men, or how fast the children can work compared to the men and women.

The problem can be solved if the wording means that the work can be completed in 20 5-hour workdays by either a group of 5 men, or a group of 7 women, or a group of 8 children.

SOLUTION FOR THE SOLVABLE PROBLEM:
If 5 men can complete the work in 20 days working 5 hours per day ( total),
each man would complete of the work in 1 hour.
If 7 women would complete the work in 20 days working 5 hours per day (100 hours total),
each woman would complete of the work in 1 hour.
If 8 children can complete the work in 20 days working 5 hours per day (100 hours total),
each child would complete of the work in 1 hour.
If all of the above is true, the fraction of the job that a group made up of 7 men, 9 women, and 10 children would complete in 1 hour is

So to complete the work at the rate of jobs per hour they will need hours.
Working 7 hours per day, that time would amount to
days, which is approximately 3.8 days.
I would say that is 4 days.

RELATED QUESTIONS

10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If a woman works for 3 1/2 hours per day, she can finish a piece of work in 10 days. How... (answered by Theo)
Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many... (answered by robertb,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
While working 7 hours day, A alone can complete a piece of work in 6 days and B alone in... (answered by solver91311)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)
12 women alone can complete a piece of work in 5 days, whereas 3 women and 9 children... (answered by knighty2002uk)