Question 739669: If it takes 3 people 4 hours to complete a task, how long will the same task take for 5 people?
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
3*4=12 man hours
5 people work for 12/5=2.4 hours also is 12 man hours
RELATED QUESTIONS
If it takes 4 people 6 hours to landscape a recreation area, how many hours will it take... (answered by edjones)
if 8 people take 6 hours to complete a task how long it take 10 people to complete the... (answered by ankor@dixie-net.com)
One person can complete a task in 3 minutes. A second person can complete the same task... (answered by ankor@dixie-net.com)
It takes two people 11 hours to complete a task. one person is three hours faster how... (answered by scott8148)
Three people can complete a task in 3hr. 20min. How long would it take 4 people to... (answered by stanbon)
Mary takes 3 hours to complete a task. Mary and Jim together take 2 hours to complete the (answered by checkley71)
How long will it take 20 machines to complete a task, given that it takes 12 days for 5... (answered by rfer)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
If it takes 4 hours for one person to perform a task and it takes another person 3 hours... (answered by flame8855)