SOLUTION: two machines are used to stamp metal parts in a factory. one requires 8 hours to stamp the needed parts, the other requires 6 hours. how long would it take both working together.
Algebra.Com
Question 736289: two machines are used to stamp metal parts in a factory. one requires 8 hours to stamp the needed parts, the other requires 6 hours. how long would it take both working together.
Answer by solver91311(24713) (Show Source): You can put this solution on YOUR website!
If A can do a job in x time periods, then A can do
of the job in 1 time period. Likewise, if B can do the same job in y time periods, then B can do
of the job in 1 time period.
So, working together, they can do
of the job in 1 time period.
Therefore, they can do the whole job in:
time periods.
John

Egw to Beta kai to Sigma
My calculator said it, I believe it, that settles it
RELATED QUESTIONS
An old-model machine can stamp 1000 parts in 4 hours. A new-model machine can stamp 1000... (answered by bucky)
Hi,
I would like to say thank you in advance.
My question is:
A certain punch... (answered by josgarithmetic,Boreal)
A certain punch press requires 3h longer to stamp a box of parts than does a newer-model (answered by Boreal,josmiceli)
An old-model machine can stamp 1000 parts in 4 hours, but his helper would require 6... (answered by checkley75)
A manufacturer has two machines available to stamp out a design. One machine has a setup... (answered by JulietG)
A letter weighs 90 grams. One stamp is needed for each 28 grams or portion thereof. How... (answered by josmiceli)
Can you help me with this problem?
A metal bar, 60 cm long, is to be divided into four (answered by lwsshak3)
Jenny examined the 14 machine parts made in an hour at a factory. She found that 3 of the (answered by Boreal)
3 machines produce the same parts at the same rate. They complete the parts in 1.2 hours. (answered by FrankM)