SOLUTION: Twenty men can finish the job in 30 days. Twenty five men were hired at the start and 10 quit after 20 days. How many days will it take to finish the job?

Algebra.Com
Question 735506: Twenty men can finish the job in 30 days. Twenty five men were hired at the start and 10 quit after 20 days. How many days will it take to finish the job?
Answer by josgarithmetic(39625)   (Show Source): You can put this solution on YOUR website!
You need to determine the rate of work of 1 man. The rate should be in Jobs per Day or as Jobs per Number of Days.

If 20 men do the job in 30 days,
Then 1 man needs 20 times longer to do the job if working alone,
Which means 1 man does the job in 30*20 days,
Or
One man works at the rate of 1 job per 600 days.

We can use (rate)*(time)=(jobs), and the idea that men working together will ADD their rates through simple addition. Remember, now we know one man works at the rate of 1 job per 600 days.

Twenty-five men worked for 20 days. How much job was done?
The rate of 25 men would be , so the amount of work done in this time was job.

After 20 days, 10 men quit and the other 15 men stayed; so now, there be just 15 men to finish the job. The question is, how much time for these remaining 15 men to finish?

How much job must these 15 men do? job must these 15 men do. What is the work rate of these 15 men together? Their rate is jobs per day.

The time is calculable in , from which divide b.s. by r, . That would be for finding number of days to finish. Plug in all the numbers.

days, and be sure to simplify before doing the final computing.
(Looks like about days).

RELATED QUESTIONS

Twenty men can finish the job in 20 days. Twenty men were hired at the start and 10 quit... (answered by richwmiller)
twelve men can finish the job in 20 days. Five men were working at the start and after 10 (answered by lwsshak3)
Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days... (answered by ankor@dixie-net.com,josgarithmetic)
80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the... (answered by josmiceli,Theo)
A contractor estimates that he could finish a project in 15 days if he has 20 men. At the (answered by josmiceli)
28 peons can finish the job in 60 days,. At the start of 16th day 5 peons were laid off... (answered by jorel1380)
Twenty laborers could finish a certain construction job in 35 days. After 11 days, five... (answered by Abbey)
twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop... (answered by Alan3354)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)