SOLUTION: if 3 men can dig 6 trenches in 4 days, how many days would it take for 24 trenches to be dug by 4 men?

Algebra.Com
Question 729825: if 3 men can dig 6 trenches in 4 days, how many days would it take for 24 trenches to be dug by 4 men?
Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
Rate is units of trenches per day. Find the rate of 1 man. One man is 1/3 of three men. His rate is therefore of trenches per day. This one-man rate is trench per day.

Now you have rate*time=trenches. For 4 men doing this work, , where is how many days for four men to dig 24 trenches. Find .

RELATED QUESTIONS

A soakaway was dug by 5 men in 24 days.How many days would it take 15 men to dig,if they... (answered by josgarithmetic,MathLover1,ikleyn)
it takes 3 men to dig 2 identical trenches in 5 hours.If all the men work at the same... (answered by josmiceli,MathTherapy)
Four men can dig a 40 foot well in 4 days. How long would it take for 8 men to dig a 60... (answered by Alan3354,ankor@dixie-net.com)
if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
if it takes 4 men 12 days to dig a hole, how long would it take 6... (answered by ptaylor)
If 3 men take 4 days to dig a drain how long would it take 2 men (answered by josgarithmetic)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
If it takes twelve men 8 days to dig a trench how many men does it take in 6... (answered by josgarithmetic)