SOLUTION: father can finish a certain job in 8 days while his daughter can finish the same job in 16 days. they start working together after 4 days the daughter leaves and his father alone f

Algebra.Com
Question 714715: father can finish a certain job in 8 days while his daughter can finish the same job in 16 days. they start working together after 4 days the daughter leaves and his father alone finishes the work. How many days did it take the fateher to finish the job?
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
They work together for 4 days
Add their rates of working

Multiply both sides by



They complete 3/4 of the job, there
is 1/4 of the job left to do
( fraction of the job left ) / ( father's rate ) = time to finish


It takes the father 6 days to finish the job

RELATED QUESTIONS

A man can do a job in 9 days and his son can do the same job in 16 days. They start... (answered by ptaylor)
Joshua can finish a certain job in 4 days while Kevin can finish the same job in 2 days.... (answered by stanbon)
Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days... (answered by ankor@dixie-net.com,josgarithmetic)
A can finish a certain job in 12 days . A&B can finish same job in 8 days.how many day... (answered by nerdybill)
A father can do a job in 3 days,and his son can do the same job for 5 days.How long will... (answered by josgarithmetic)
A does a job in 6 days while B can do the same job in 4 days. how long will it take A and (answered by josgarithmetic)
joe can do a job in 3 days, while jill can do the same job in 6 days. How long will they... (answered by ikleyn)
3 men and 6 women finish a job in 9 days while 2 men and 8 women finish it in 12 days.in... (answered by josgarithmetic)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)