SOLUTION: Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days ahead of schedule, how many men will be needed?

Algebra.Com
Question 706108: Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days ahead of schedule, how many men will be needed?
Found 2 solutions by nshah11, hibiskus:
Answer by nshah11(47)   (Show Source): You can put this solution on YOUR website!
If 8 men can finish a painting job in 10 days, then each man can complete 1/80th of the job per day.
If the task needs to be completed 2 days ahead of schedule, 1/8 of the job must be completed by the workers per day => x/80 = 1/8 => x= 10 workers

Answer by hibiskus(3)   (Show Source): You can put this solution on YOUR website!
Inversely Proportional: when one value decreases at the same rate that the other increases. Than in our examples
when days coming down number of men goes up and we have
for directly propotional
If x then y. If x is changed to a then what will be the value of y?
formula
x->y
a->
for Inversely propotional
If x then y. If x is changed to a then what will be the value of y?
formula
x->y
a->
Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days ahead of schedule, how many men will be needed?
If 10 then 8. If 8 then how many?
10->8
8->
the result is 10 men to finish a paininting job in 8 days. :)

RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
eight men can complete a job in 25 days. how many men will be needed to complete the job... (answered by psbhowmick)
1.four men can paint a house in 24 days.the owner wants the painting job to be finished... (answered by stanbon)
a piece of work can be done by 40 men in 48 days. after 15 days, 18 men were transferred... (answered by stanbon)
15 men complete a job in 10 days, 8 men finish same job ? how many... (answered by josgarithmetic)
Fifteen carpenters can complete building a house in 45 days . How many extra men will be... (answered by ankor@dixie-net.com)
A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
a piece of work can be done by 40 men in 48 days, after 15days, 18 men were transferred... (answered by ankor@dixie-net.com)