SOLUTION: X can do (1/4) of work in 10 days. Y can do 40% of the work in 40 days and Z can do (1/3) of the work in 13 days. Who will complete the work first?

Algebra.Com
Question 705817: X can do (1/4) of work in 10 days. Y can do 40% of the work in 40 days and Z can do (1/3) of the work in 13 days. Who will complete the work first?
Answer by MathLover1(20849)   (Show Source): You can put this solution on YOUR website!

if can do of work in days, means need times more days to complete the whole work: so, whole work will be done by in days

if can do % = of the work in days; so,whole work will be done by in ...=>... ...=>... days

and, if can do of the work in days, means need times more days to complete the whole work:
so, whole work will be done by in days
Therefore, will complete the work first.

RELATED QUESTIONS

Patsy can do 1/4 of a work in 10 days. Quincy can do 40% of the work in 15 days and... (answered by Edwin McCravy)
X can do 1/8th of work in 10 day Y can do 60% of the work in 60 days and Z can do 1/5 of... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 40/3 days. A alone can do the work in 20 days. How long (answered by mananth)
A can do 1/3 of certain work in 10 days and B can do 2/5 of the same work in 8 days find... (answered by robertb)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A can do a piece of work in 60 days, which B can do in 40 days. Both started the work but (answered by ikleyn)
A can do 1/3 of a work in 5 days and B can do 2/5 of the work in 10 days. In how many... (answered by Edwin McCravy)
A can do 1/3 of a work in 5 days and B can do 2/5 of the work in 10 days. How many days... (answered by richwmiller)
2 men can do the same amount of work that 3 boys can do. 4 men and 10 boys can do a piece (answered by josgarithmetic)