Question 690681: Suppose that 5 workers can complete a certain task in 12 days. If there are 15 workers, how many days would it take for them to finish the same task?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
Suppose that 5 workers can complete a certain task in 12 days.
Find the number of man-days to complete
5 * 12 = 60 man-days
;
If there are 15 workers, how many days would it take for them to finish the same task?
let d = number of days required if there are 15 men
15d = 60
d = 60/15
d = 4 days for 15 men to do the job
RELATED QUESTIONS
Suppose that
6
workers can complete a certain task in
10
days. If there are
20
(answered by josgarithmetic)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
Ho long will it take 6 workers to complete a task, give that 7 workers can complete the... (answered by solver91311,Edwin McCravy,stanbon)
how long will it take 18 workers to complete a task, given that it take 9 days for 8... (answered by boilpoil)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
If 20 workers can complete a task in 12 hrs, how long will it take 30... (answered by josgarithmetic)
If 9 workers can complete 12 chairs in 3 days,how long will it take 4 workers to complete (answered by math_helper,ankor@dixie-net.com)
If 9 workers can complete 12 chairs in 3 days, how long will it take 4 workers to... (answered by josgarithmetic,MathTherapy)