Question 685827: A and B working together can finish a job in T days. If A works alone and completes the job, he will take T + 5 days. If B works alone and completes the same job, he will take T + 45 days. What is T?

Found 2 solutions by Edwin McCravy, josmiceli:
Answer by Edwin McCravy(20054)   (Show Source): You can put this solution on YOUR website!
A and B working together can finish a job in T days. If A works alone and completes the job, he will take T + 5 days. If B works alone and completes the same job, he will take T + 45 days. What is T?
Their combined rate is 1 job per T days or  or 

A's rate is 1 job per T+5 days or  or 

B's rate is 1 job per T+45 hours or  or 

The equation comes from  +  = 

                                      +  = 

Multiply through by LCD = T(T+5)(T+45) and solve.  You'll get T = 15 days.

Edwin


Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
A's rate working alone is
B's rate working alone is
Working together:

Multiply both sides by





RELATED QUESTIONS

A and B working together can finish the job in 10 days. if A works 4 days and B works 3... (answered by josgarithmetic,ikleyn)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A,B, and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by edjones)
a,b and c can finish a job in 6 days. if b and c work together , the job will take 9... (answered by venugopalramana)
A,B,and C can finish a job in six days. If B and C work together, the job will take 9... (answered by ankor@dixie-net.com,josmiceli)
A B and C can finish a job in 6 days. If B and C work together the job will take 9 days.... (answered by josmiceli)
A, B, and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by richwmiller)
A, B, and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by richwmiller)
A, B, and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by Edwin McCravy)