SOLUTION: It takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate
Algebra.Com
Question 680851: It takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
It takes 6 people 6 days to do a job
It would take 1 person 6 times as long to do the job, so
It takes 1 person 36 days to do the job
2 people can do the job in half the time, so
It takes 2 people 18 days to do the job
RELATED QUESTIONS
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
If it takes 4 days for 6 people to finish a job, than how many days does it take 8 people (answered by stanbon)
If 4 people take 6 days to do a painting job, how many days will it take 3 people to do... (answered by josmiceli,Edwin McCravy)
It takes 6 people a total of 12 days to paint a wall.
How long it would take 4 people to (answered by Edwin McCravy,saw,ikleyn)
It takes 5 people 6 days to paint a house, working 8 hour shifts.
a) how long would... (answered by ikleyn)
Pls help: "it takes 6 people 10 hours to complete a certain job. How many hours will it... (answered by robertb,Edwin McCravy)
It took 6 people 4 days to complete a concrete project. How many days would it take 2... (answered by richwmiller)
It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the... (answered by Maths68)
It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the... (answered by josgarithmetic,rothauserc)