Question 667189: A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C alone can do it in 40 days. In how many days A alone will do the work?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
A,B and C can do a piece of work together in 15 days.
B alone can do it in 30 days and C alone can do it in 40 days.
In how many days A alone will do the work?
:
Let a = no. of days required by A alone
let the completed job = 1
:
A typical shared work equation
:
+ + = 1
Reduce the fractions
+ + = 1
multiply by 8a, results
8(15) + 4a + 3a = 8a
120 + 7a = 8a
120 = 8a - 7a
a = 120 hrs A working alone
:
:
see if that adds up using a calc
+ + =
.125 + .50 + .375 = 1; confirms our solution

RELATED QUESTIONS

A and B can do a piece of work in 12 days , B and C can do it in 15 days and C and A can... (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a... (answered by ikleyn)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
A and B can do a piece of work in 40/3 days. A alone can do the work in 20 days. How long (answered by mananth)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)