Question 658838: Crew No. 1 can finish installation of an antenna tower in 200 man-hour while Crew No. 2 can finish the same job in 300 man-hour. How long will it take both of the crews to finish the same job, working together?
Answer by checkley79(3341)   (Show Source): You can put this solution on YOUR website!
1/200+1/300=1/X
FIND A COMMON DENOMINATOR FOR THE 2 FRACTIONS.
200 400 600 800
300 600 900 600 LOOKS LIKE A SOLUTION.
(3*1+2*1)/600=1/X
(3+2)/600=1/X
5/600=1/X
5X=600
X=600/5
X=120 HOURS ANS.

RELATED QUESTIONS

One crew can detassel a field of corn in 6 days. Another crew can do the same job in 4... (answered by ankor@dixie-net.com)
One roofing crew of 5 can finish A 3,800-foot roof in 15 hours, ans another crew of 6 can (answered by richwmiller)
Michael and John work together building houses. Michael's crew can build a house in 8... (answered by jorel1380,ikleyn)
One roofing crew can finish a 2,800-square-foot roof in 12 hours, and another crew can do (answered by josgarithmetic)
2 men and 5 boys together can a finish a piece of work in 4 days ,while 3 men and h boys... (answered by richwmiller)
A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
The fraction of work done by a man who can finish a job in 2 hours. in mathematical... (answered by ikleyn)
A library crew can shelf books in six hours. Another crew can do the job in four hours.... (answered by lwsshak3)
Janet can do a job in 3 hours while Garry can do the same job in 2 hours. If Janet works... (answered by josgarithmetic,MathTherapy)