SOLUTION: Working 8 hours a day, 24 men do a piece of work in 15 days. Find how many days it would take 16 men working 9 hours a day, to do the same piece of work

Algebra.Com
Question 657887: Working 8 hours a day, 24 men do a piece of work in 15 days. Find how many days it would take 16 men working 9 hours a day, to do the same piece of work
Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!
 
Hi,
Working 8 hours a day, 24 men do a piece of work in 15 days
how many days it would take 16 men working 9 hours a day

|| Solve for x
RELATED QUESTIONS

Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
15 men working 6 hours a day can do a piece of work in 20 days. how many men working 8... (answered by sadike007)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
if 4 men can mow certain piece of land in 6 days ,working 10 hours a day, how many days... (answered by Alan3354,stanbon)
If 12 men working 8hrs a day can do a piece of work in 15 days, how many hrs a day must... (answered by stanbon)
if four men do a piece of work in 8 days how many days will it take 16 men working at the (answered by ewatrrr)
It will take 24 men working 9 hours a day each to build a house in 45 days. Given that... (answered by lwsshak3)
If 15 men , woking 9 hours a day, can reap a field in 16 days , in how many days will 18... (answered by ankor@dixie-net.com)