SOLUTION: A does a work in 20 days. A did for 28 days. Then b came. They together take 76 days to complete the 7 job. Find howmany days B complete a work.
Algebra.Com
Question 625647: A does a work in 20 days. A did for 28 days. Then b came. They together take 76 days to complete the 7 job. Find howmany days B complete a work.
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
Rewrite to show how I understand the problem
:
A does a work in 20 days. A worked for 28 days.
Then B came. Working together, they take 76 days to complete 7 jobs.
Find how many days it takes B to complete a work.
:
let b = time for B to do one job by himself
let one completed job = 1
:
+ = 7
+ = 7
multiply by 20b
104b + 20(76) = 20b(7)
104b + 1520 = 140b
1520 = 140b - 104b
1520 = 36b
b =
b = 42.22 days to do one job alone
RELATED QUESTIONS
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by stanbon)
2 persons a and b they can complete a certain work in 16 and 20 days they work together... (answered by anand429)
A takes 20 days to complete a job X. B takes 30 days to complete the same job X. How... (answered by CubeyThePenguin)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by richwmiller)
If totally 25 workers working for 7 hours a day completing a particular piece of work in... (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days... (answered by richwmiller)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)