Question 621276: Printing Press A starts working on a job at 8:00 am. Working alone, press A would take 24 hours to do the job. At 9:30 am, press B also begins to run the same job as A. Press B is twice as fast as press A. What time will the job be completed?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
How much of the job did press A get done in 1.5 hrs
from 8 AM to 9:30 AM?
A's rate is ( 1 job ) / ( 24 hrs )
In 1.5 hrs:
job/hr
Now both A and B work on job
There is
of the job left to do.
B's rate is ( 1 job ) / ( 12 hrs )
Multiply both sides by
In 7.5 hrs after B starts, the job is done
9:30 + 7.5 = 5 PM job is done
check answer:
OK
RELATED QUESTIONS
a printing shop starts a job at 10 A.M. on press A. Using this press alone, it would take (answered by richwmiller)
A printing shop starts a job at 10 a.m. on press A. Using this press alone, it would take (answered by richwmiller)
a printing shop starts a job at 10 a.m. on press A. Using this press alone, it would take (answered by richwmiller)
Two printing presses, working together, can complete a job in 2 hours. If one press... (answered by ptaylor)
two printing presses working together can complete a job in 2.5hours.working alone,press... (answered by stanbon)
tutor quick help plz and solution. One printing press can finish a certain job in 1 1/2... (answered by richwmiller)
Printing press A can print an order in 7hours. If printing press B is used along with... (answered by Edwin McCravy,dolly)
Two printing presses can complete a job in 2 hours. if one requires 6 hours to do the job (answered by checkley75)
A printing press can print a newspaper in 4 hours. After the press has worked for one... (answered by richwmiller)