SOLUTION: an electrical contractor is planning to complete a lighting job by useing two separate crews. Both crews working together would require 20 days to complete the entire job. The fi

Algebra.Com
Question 618384: an electrical contractor is planning to complete a lighting job by useing two separate crews. Both crews working together would require 20 days to complete the entire job. The first crew working alone would require 60 days to complete the entire job. Assume that all workers maintained their same rate of doing the work, whether working individulally or collectively. How many days would it take for the second crew, working alone to complete the job?
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
20/60+20/x=1
20/x=2/3
x=30
check
20/60+20/30=1
1/3+2/3=1
1=1
ok

RELATED QUESTIONS

Two crews can complete a job in 45 days when working together. On their own, one crew... (answered by ankor@dixie-net.com)
Two digging crews are competing for a job the first team shows they can dig a foundation... (answered by josgarithmetic)
It takes crew A 4 hours to paint a room. It takes crew B 5 hours to do the same job. How... (answered by josmiceli,Edwin McCravy)
Crew No. 1 can finish installation of an antenna tower in 200 man-hour while Crew No. 2... (answered by checkley79)
A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
Two road crews, working together, repaired 1 mile of road in 4 hours. Working separately, (answered by checkley71)
One road crew can pave a section of highway in 15 h. A second crew can do the same job in (answered by josgarithmetic,ikleyn,Alan3354,greenestamps)
A hurricane strikes and a rural area is without food or water. Three crews arrive. One... (answered by edjones)
Find the domain of f(x)=x-3 ___ x-6... (answered by solver91311)