Question 616137: it takes 10 people to complete 1 task in 30 days how many people will complete the same task in 3 days
Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!
 
Hi,
it takes 10 people to complete 1 task in 30 days
how many people will complete the same task in 3 days: 100 People
Note: Work = Work
10·30days = x·3days
300/3 = x = 100
RELATED QUESTIONS

If it takes 20 people to complete as task in 12 days. How many people will it take to... (answered by Edwin McCravy)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
how many machines will it take to complete a task in 3 days, considering it takes 10 days (answered by stanbon)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)
How many machines will be needed to complete a task in 15 days, given that 6 machines can (answered by stanbon)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
If it takes 3 people 4 hours to complete a task, how long will the same task take for 5... (answered by richwmiller)