Question 612501: 16 people finishes 2/3 of the job in 7 days, how many people can finish remaining job in 2 days
Answer by lwsshak3(11628) (Show Source): You can put this solution on YOUR website!
16 people finishes 2/3 of the job in 7 days, how many people can finish remaining job in 2 days
**
man-days required to finish 2/3 of the job=7*16=112
man-days required to finish remaining 1/3 of the job=112/2=56
people required to finish the job=56/2=28
RELATED QUESTIONS
If 3 people finish a given job in 8 days,how many days will it take for 2 people to... (answered by ptaylor)
Seven people can do 1/3 of a job in 45 days. How many additional people must be hired to... (answered by josmiceli)
i have solved that if Worker A finishes a job in 8 days and worker B finishes it in 12... (answered by josmiceli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
ABC can finish the job in 2 days altogether. A can finish it alone in 5 days. B can... (answered by ewatrrr)
father can finish a certain job in 8 days while his daughter can finish the same job in... (answered by josmiceli)
If 10 people can finish a job in 30 days, In how many the job can be completed by 30... (answered by checkley79)
A group of 10 men can do a job in 50 days. They start the work together, but after x... (answered by scott8148)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)