SOLUTION: 6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench at the same rate?

Algebra.Com
Question 612143: 6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench at the same rate?
Answer by Edwin McCravy(20056)   (Show Source): You can put this solution on YOUR website!
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench at the same rate?

Since 6 men can dig a trench in 3 days, 3 times as many men, or 18 men,
can do it in 1/3 the time or just 1 day.

So half of 18 men, or 9 men, will take twice as long as 18 men, or 2 days.

--------------------------------------------------------

Another way to do it is that this fraction must stay constant:

WORKERS × TIME     WORKERS × TIME
——————————————  = ——————————————    
     JOBS               JOBS


     6 × 3            9 × T 
     —————     =     ————————
       1                1

       18            9T 
      ———     =     —————
       1             1
 
       18    =     9T

        2    =     T

   
2 days.

Edwin


RELATED QUESTIONS

if 12 men can dig a trench in 8 days, how many men can dig it in 6 days at the same rate? (answered by josmiceli,ptaylor)
Ten men can dig a trench in 4 days.How many men would dig the same trench in 2... (answered by Alan3354,ankor@dixie-net.com)
Two men dig a trench 30 m long in 3 days. How long would it take 3 men to dig a trench 15 (answered by ikleyn)
If it took 8 labourers 28 days to dig a trench,how long will it take 6 labourers working... (answered by stanbon,Edwin McCravy)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
it takes 8 men 9 hours to dig a trench.how long would it take 6 men to dig the trench if... (answered by ankor@dixie-net.com)
If 12 men can dig a trench in 8 days how many men can dig it in 6... (answered by josgarithmetic,greenestamps)
If it takes twelve men 8 days to dig a trench how many men does it take in 6... (answered by josgarithmetic)
It takes 18 men 6 hours to dig a trench 720 feet long. Working at the same rate, how... (answered by ankor@dixie-net.com)