SOLUTION: 20 men can do a piece of work in 24 days. After working for six days an additional number of men is taken to finish the piece of work in 21 days from the beginning. Find the number

Algebra.Com
Question 603164: 20 men can do a piece of work in 24 days. After working for six days an additional number of men is taken to finish the piece of work in 21 days from the beginning. Find the number of additional men?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
"20 men can do a piece of work in 24 days."
Find the number of man-days to complete the job
20 * 24 = 480 man-days
;
After working for six days an additional number of men is taken to finish the piece of work in 21 days from the beginning.
:
let a = no. of additional men
(20*6) + 15(a+20) = 480
120 + 15a + 300 = 480
15a = 480 - 420
a =
a = 4 additional men required to finish in 21 days
:
:
Check this
120 + 15(24) = 480

RELATED QUESTIONS

20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
10 men can do a piece of work in 24 days. After working 6 days,few men were added to... (answered by Edwin McCravy)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
55 men can finish a piece of work in 42 days. How many additional men must be added to... (answered by josmiceli)
1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men... (answered by josgarithmetic)
Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
if 20 men can do a piece of work in 8 days, then how many men can finish the same work in (answered by ankor@dixie-net.com)
4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which... (answered by josmiceli,MathTherapy)
twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop... (answered by Alan3354)