SOLUTION: a contractor got a contract to build a building in 30 days and employed 20 men to do the work. only 1/4 work was completed in 10 days. how many more men be employed so that the wor

Algebra.Com
Question 600444: a contractor got a contract to build a building in 30 days and employed 20 men to do the work. only 1/4 work was completed in 10 days. how many more men be employed so that the work be completed in the specified time?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
a contractor got a contract to build a building in 30 days and employed 20 men to do the work. only 1/4 work was completed in 10 days. how many more men be employed so that the work be completed in the specified time?
:
Find the number of man-hrs to complete 1/4 of the job
20 * 10 = 200 man-days
therefore
3 * 200 = 600 man-days required to complete the job (For a total of 800 man-days)
:
Let m, = no. of additional men required to complete the job in the remaining 20 days
20(m + 20) = 600
20m + 400 = 600
20m = 600 - 400
20m = 200
m = 200/20
m = 10 additional men required to finish the job in the required 30 days
:

RELATED QUESTIONS

a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
A contractor undertook to build a building in 52 days and employed 24 men to work. Only... (answered by ankor@dixie-net.com,josgarithmetic)
A road contractor wanted to build a 200 meter long road in 30 days and employed 20... (answered by ankor@dixie-net.com,MathTherapy)
A contractor undertook to build a road in 200 days he employed 140 men after 60 days he... (answered by josgarithmetic,josmiceli,ikleyn,MathTherapy)
A contractor took a contract for 45 days and employed 110 workers. If they complete ¼ of... (answered by ankor@dixie-net.com)
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A contractor undertook a certain work to be done in 80 days and employed 72 men to do it. (answered by ankor@dixie-net.com)