Question 586466: if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate?
Found 2 solutions by ankor@dixie-net.com, eschwartz:
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate?
:
Find the number of man-days to do the job
6 * 2 = 12 man-days
:
"how long would it take 4 roofers to do the same job,"
let d = no. of days for 4 men to do it
4d = 12
d = 12/4
d = 3 days
Answer by eschwartz(9) (Show Source): You can put this solution on YOUR website!
You could also say like this:
You now have of the work force, so you will need the time.
Workers are:
Time required is:
RELATED QUESTIONS
if it takes 6 roofers 2 days to put on a new roof, how long would it take 4 roofers to do (answered by richwmiller)
working together, it takes two roofers 4 hours to put a new roof on a portable classroom. (answered by scott8148)
1) working together , it takes 2 roofers 4 hours to put a new roof on. If the first... (answered by solver91311)
If Harry can do a job in 2 days, and Sally can do the job in 4 days, and Henry can do... (answered by stanbon)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ntnk)
sam can do job in 4 days, Lisa - 6 days, Tom - 2 days. How long would the job take to... (answered by ewatrrr)
it takes doug 6 days to roof a house. if his son helps him,the job can be done in 4 days. (answered by chitra,Edwin McCravy)
The time required to accomplish a task varies inversely as the number of people working... (answered by ptaylor)
one roofer can put a new roof on a house three times faster than another. Working... (answered by chosenpoint)