SOLUTION: If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish building 4 houses. Thanks.

Algebra.Com
Question 584785: If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish building 4 houses.
Thanks.

Found 2 solutions by scott8148, Edwin McCravy:
Answer by scott8148(6628)   (Show Source): You can put this solution on YOUR website!
3 * 10 = 30 man-days per house

4 * 30 = 120 man-days for 4 houses

120 / 15 = 8 days

Answer by Edwin McCravy(20054)   (Show Source): You can put this solution on YOUR website!
If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish building 4 houses.
There are several ways to get to the answer.  

First way:
Since it takes 3 days for 10 workers to finish building one house, 
it would take those 10 workers 4 times that long to finish building 4 houses, so
it would take those 10 workers 12 days to finish building 4 houses.
It would take half as many workers twice as long to finish building 4 houses, so
it would take 5 workers 24 days to finish building 4 houses.
It would take 3 times as many workers as that only 1/3 as long to build 4 houses. So,
It would take 15 workers only 8 days to finish building 4 houses. 
  
Second way: 
Since it takes 3 days for 10 workers to finish building one house, 
it would take 3 times as many workers only 1/3 as long to finish building one house, so
it would take 30 workers only 1 day to finish building one house.
It would take half as many workers twice as long to finish building one house, so
it would take 15 workers 2 days to finish building one house.
It would take those 15 workers 4 times as long to finish building 4 houses. So,
It would take 15 workers only 8 days to finish building 4 houses.

--------------------------------------------------------------------

Still another way is to use the worker-jobs-time formula

W1 = number of workers in the first situation
T1 = time required in the first situation
J1 = number of jobs done in the first situation

W2 = number of workers in the second situation
T2 = time required in the second situation
J2 = number of jobs done in the second situation

The formula is













So it would take them 8 days.

Edwin

RELATED QUESTIONS

If it takes 3 days for 10 workers to finish a house, how many days will it take 15... (answered by ankor@dixie-net.com)
It takes 24 days for 8 workers to complete painting a building, how many days will it... (answered by josgarithmetic)
if 3 workers can finish painting a house in 2 days, how many days will it take 6 workers (answered by josgarithmetic,josmiceli,ikleyn)
Hi it takes 15 days for 10 workers working 8 hours a day to finish an order. How many... (answered by joshuajz,josgarithmetic,ikleyn,greenestamps)
Gary hired 10 workers to finish the repairs of his house in 24 days. How many workers... (answered by josgarithmetic)
When building a house, the number of days required to build is inversely proportional to... (answered by ankor@dixie-net.com)
Suppose that 5 workers can complete a certain task in 12 days. If there are 15 workers,... (answered by ankor@dixie-net.com)
Suppose that 6 workers can complete a certain task in 10 days. If there are 20 (answered by josgarithmetic)
Four workers are building a house. In five days they built half the house. But winter is (answered by ankor@dixie-net.com,greenestamps,josgarithmetic)