SOLUTION: A takes 10 days less than the time B to complete a work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
Algebra.Com
Question 579436: A takes 10 days less than the time B to complete a work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
A takes 10 days less than the time B to complete a work.
If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
:
Let b = time for B to complete the work
then
(b-10) = time for A to do it
:
Let the completed job = 1
:
A typical shared work equation
:
+ = 1
Multiply by b(b-10)
b(b-10)* + b(b-10)* = b(b-10)
Cancel the denominators
12(b-10) + 12b = b^2 - 10b
:
12b - 120 + 12b = b^2 - 10b
Combine like terms on the right
0 = b^2 -10b - 24b + 120
b^2 - 34b + 120 = 0
this will factor to
(b-30)(b-4) = 0
Two solutions
b = 4
and
b = 30 days, this is the only reasonable answer
;
:
See if checks out
12/30 + 12/20 -
.4 + .6 = 1, confirms our solution of b = 30 days
RELATED QUESTIONS
A takes 10 days less than the time taken by B to finish an embroidery work. If both A and (answered by Theo,mananth)
Person A takes 6 days less than the time taken by the person B to finish a piece of work. (answered by stanbon,ikleyn)
A can finish the work in 6 days less than the time taken by B to finish the work.If both... (answered by ankor@dixie-net.com)
A takes 6 days less than the time taken by B to finish the piece of work.if A and B... (answered by josgarithmetic)
A can do a piece of work in 30 days,and B can do the same work in 40 days,if both do... (answered by richwmiller)
A takes half time than B to do a work. C takes time equal to A and B together. If three... (answered by josmiceli)
Please solve this question : two persons A and B together can do work in 10 days. the... (answered by richwmiller)
A takes 5 days to finish a work, B takes 8 days to finish the same work. If A,B,C... (answered by josgarithmetic,ikleyn)
A can do a piece of work in 10 days. If A and B work together they can finish it in 6... (answered by Narsinghchauhan8960103366)