SOLUTION: If it takes 20 people to complete as task in 12 days. How many people will it take to complete the task in 8 days?

Algebra.Com
Question 576817: If it takes 20 people to complete as task in 12 days. How many people will it take to complete the task in 8 days?
Answer by Edwin McCravy(20054)   (Show Source): You can put this solution on YOUR website!
If it takes 20 people to complete a task in 12 days. How many people will it
take to complete the task in 8 days?

We have two quantities, the number of people and the number of days.
We first have to decide whether the two quantities are DIRECTLY
proportional or INVERSELY proportional:

The fraction on the left will contain one quantity "before" and "after",
and the fraction on the right will contain the other quantity "before"
and after.

Direct variation:

When one quantity is INcreased the other quantity is also INcreased, and when
one quantity is DEcreased to other quantity is also DEcreased.

If that is the case, then we use this
proportion:



Inverse variation:

When one quantity is increased the other quantity is decreased, and when one
quantity is decreased the other quantity is increased.

If that is the case, then we have INVERSE variation, and so we must INVERT the
second ratio above.



We have to decide whether PEOPLE and DAYS are DIRECTLY or
INVERSELY proprotional.  So we ask which of these is true:

1. DIRECTLY{  The MORE people we have working, the MORE days it will take and
the FEWER people we have working, the FEWER days it will take them.

or

2. INVERSELY: The MORE people we have working, the FEWER days it will take and
The FEWER people we have working, the MORE days it will take them.


Obviously 1 is false and 2 is true

So they are NOT directly proportional so this proportion does not work: 



Since the quatities people and days are INVERSELY proportional we INVERT 
the second ratio and we have this instead:




People in 1st situation = 20
People in second situation = ????  (Let that be N people)
Days in 1st situation = 12
Days in second situation = 8

 = 

8N = 240
 N = 30

So it will take 30 people to complete the task in 8 days.

Edwin

RELATED QUESTIONS

it takes 10 people to complete 1 task in 30 days how many people will complete the same... (answered by ewatrrr)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)
John can complete a task in 18 days while Peter can complete it in 12 days. How many days (answered by math_helper)
How long will it take 20 machines to complete a task, given that it takes 12 days for 5... (answered by rfer)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
how many machines will it take to complete a task in 3 days, considering it takes 10 days (answered by stanbon)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
please if it takes 2 works 2 weeks to complete a task, how many days will it take 5 works (answered by Fombitz)
It takes Jose 12 days to complete a task. The same task would take Hans 24 days. After... (answered by mananth)