Answer by neatmath(302) (Show Source): You can put this solution on YOUR website!
In order to solve this,
we need to find out how many man-days it takes to plough the whole field.
It is simple to see, that if it takes 8 men 9 days to do the whole job,
then it will take them 9*8, or 72 man-days to complete the job.
Now, we can find out how many days it would take 18 men to do the job.
It would still take a total of 72 man-days to do the job,
but this time, we have 18 men instead of 8.
Simply divide 72 by 18, and we will have our answer.
Thus it would take 18 men only 4 days to plough the field.
Algebraically, we would have written it:
This type of problem is actually MUCH simpler to do than the ones involving filling pools and buckets.
*******************************************************
I hope this helps! :)
Email Scott: neatmath@yahoo.com for help with specific problems,
or to inquire about mathematics tutoring via email or other methods.
Paypal is always accepted for single problems or for more intensive tutoring!
Single problems would range from 50 cents to 5 dollars each, depending on their complexity.
RELATED QUESTIONS
If 8 men can plough a field in 9 hours, how long would it take 18 men at the same rate?
(answered by josmiceli)
if four men do a piece of work in 8 days how many days will it take 16 men working at the (answered by ewatrrr)
It will take 24 men working 9 hours a day each to build a house in 45 days. Given that... (answered by lwsshak3)
If 6 men do a job in 12 days, how long would 18 men take, working at the same rate?
HEY... (answered by Alan3354)
4 men can do a piece of work in 8 days how many days would it take
16 men at the same... (answered by Edwin McCravy,ikleyn,josgarithmetic,greenestamps)
if 9 men can do a piece of work for 20 days, how long would it take 4 men to do do,... (answered by josgarithmetic)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
If 9 men take 15 days to tile the floors of a house, how long will it take five men... (answered by richwmiller)