Question 535024: there were 4 workers that built A WALL IN 5 DAYS AND THERE 10 WORKERS HOW MANY DAYS DID IT TAKE THEME TO BUILT A WALL
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
there were 4 workers that built A WALL IN 5 DAYS
Find how many man-days to complete wall:
4 * 5 = 20 man-days
:
"THERE 10 WORKERS HOW MANY DAYS DID IT TAKE THEM TO BUILd A WALL?
let d = no. of days for 10 guys to do it
10d = 20
d = 2 days for 10 guys to do it
:
:
This is in theory only, usually when you get that many together, at least two of them are goof-offs. If they are city workers, the no. of goof-offs will quadruple.
:
However, your teacher probably is not interested in the social aspect of the situation, have a Blessed Thanksgiving! C

RELATED QUESTIONS

Suppose that 6 workers can complete a certain task in 10 days. If there are 20 (answered by josgarithmetic)
Suppose that 5 workers can complete a certain task in 12 days. If there are 15 workers,... (answered by ankor@dixie-net.com)
in a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine... (answered by ankor@dixie-net.com)
There was 12 workers and to complete the job will take 5 weeks and each week is 5 days... (answered by josgarithmetic,ptaylor,MathTherapy)
Two teams of workers have to a work in 6 days. After the that the first team worked 5... (answered by ptaylor)
2 men and 6 boys can build a wall in 4 days, 4 men and 4 boys can do the same job in 3... (answered by ewatrrr)
A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
A crew of ten workers was hired to complete a job in 8 days. After working for two days,... (answered by josmiceli,MathTherapy)
There are 4 men making a house. One guy can make it in 2 days , another guy in 10 days,... (answered by josgarithmetic,moemoe)