SOLUTION: it takes 5 workers 9 days to build a barn? how many days would it take 3 workers to build a barn? extra credit: if a the barn needs to be build in 7 days, what is the number of

Algebra.Com
Question 520556: it takes 5 workers 9 days to build a barn? how many days would it take 3 workers to build a barn?
extra credit:
if a the barn needs to be build in 7 days, what is the number of workers needed?

Found 2 solutions by oberobic, bucky:
Answer by oberobic(2304)   (Show Source): You can put this solution on YOUR website!
With job problems like this, it is best to look at the problem as a question of fractions.
.
a crew of 5 workers can build a barn in 9 days
the crew builds 1/9 of the barn per day
each worker is 1/5 of the crew
each worker builds 1/45 of the barn per day
.
5 workers * 1/45 barn/day * 9 days = 45/45 barn = 1 barn
.
3 workers * 1/45 barn/day * x days = 1 barn
3 * 1/45 * x = 1
3/45*x = 1
3x = 45
x = 15 days
.
Done.

Answer by bucky(2189)   (Show Source): You can put this solution on YOUR website!
Another tutor has given you a good explanation of the team effort it takes for 5 men finishing the job in 9 days. Each man does of the job per day. In that way, if the team consists of just 3 men, it takes that team 15 days to do the job.
.
That being the case, for the extra credit part:
.
If the job needs to be done in 7 days, each day the team of "x" number of men needs to do of the job each day. Since each team member does of the job in a day, if you multiply that times the unknown number of men, the answer must equal . In equation form this can be written as:
.

.
You can solve this equation for "x" by multiplying both sides of the equation by 45 as follows:
.

.
On the left side the multiplier of 45 cancels with the denominator and you are left with:
.

.
When you divide out the right side you get the answer .
.
Since of a person is not realistic, 6 men will NOT complete the job in 7 days. Therefore, 7 men will complete the job before the end of the 7th day.
.
Consider this ... 7 men, each doing of the job per day will complete of the job per day. Therefore, is 7 days they will do of the job. This tells you that in 7 days they will complete of the job ... in other words the 7 man team in 7 days will have the capability to complete the 1 job and do a little more work on another job too.
.
Hope this helps you score the extra credit.

RELATED QUESTIONS

formulate an algebraic expression to solve how many days it takes 3 masons to build a... (answered by Fombitz)
if it takes 6 days for 6 workers to build a garage, how long would it take 9... (answered by Edwin McCravy,ikleyn,greenestamps)
3 workers can build a small barn in 24 days. How many workers are needed if we want to... (answered by stanbon)
It takes 12 workers 30 days to build a house. How long would it take 18 similar workers? (answered by ramkikk66)
It takes three workers four days to build a wall. How long will it take two workers to... (answered by ewatrrr)
Please help me solve the following problem: If it takes 80 workers 10 days to build 12... (answered by ewatrrr)
if 6 workers can build 4 cars in two days then how many days would it take 8 workers to... (answered by oberobic,ankor@dixie-net.com)
of 5x workers can build a car in 4y days how many days will it take 2z work at the same... (answered by josgarithmetic)
The number of days required to build a bridge is varies inversely to the number of... (answered by josmiceli)