Question 505011: If 4 men can do the job in 9 days,how many men were needed to do the job in 12 days?
Answer by Edwin McCravy(20081) (Show Source):
You can put this solution on YOUR website! If 4 men can do the job in 9 days,how many men were needed to do the job in 12 days?
Since 4 men can do the job in 9 days, then it would take 1 man 4 times as long or 36 days.
12 days is 3 times as fast as the 36 days it would take 1 man, so it will take
3 men.
---------------------------------
Or you can use the formula
W1*T1 W2*T2
----- = -----
J1 J2
where
W1 = number of workers in the first ssituation = 4
T1 = number of days in the first situation = 9
J1 = number of jobs in the first situation = 1
W2 = number of workers in the second ssituation = ?
T2 = number of days in the second situation = 12
J2 = number of jobs in the second situation = 1
4*9 W2*12
--- = -----
1 1
36 = 12W2
3 = W2
Edwin
|
|
|
| |