SOLUTION: The erection of a tower takes 24 men to complete in 15 days. How many days will it take 9 men to erect if they work at the same rate?

Algebra.Com
Question 498803: The erection of a tower takes 24 men to complete in 15 days. How many days will it take 9 men to erect if they work at the same rate?
Answer by ptaylor(2198)   (Show Source): You can put this solution on YOUR website!
If 24 men can complete the tower in 15 days, there are 24*15=360 man-days of labor involved in the project
In other words, 1 man can complete the project in 360 days.
9 men can complete the job in 360/9=40 days
And, of course, it takes 24 men 360/24=15 days to complete the job
Another way:
Let x=number of days it takes 9 men to do the job
The men work at the rate of 1/360 of the project per day
so, (9/360)*x=1 (1 tower, that is)
9x=360
x=40 days
Hope this helps---ptaylor



RELATED QUESTIONS

If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES... (answered by josgarithmetic,Alan3354,greenestamps,MathTherapy)
If a piece of work could be completed in 24 days by 98 men how many men would it take (answered by Alan3354)
A soakaway was dug by 5 men in 24 days.How many days would it take 15 men to dig,if they... (answered by josgarithmetic,MathLover1,ikleyn)
It takes 20 men 60 days to complete a building work.how many days longer would it take 15 (answered by mananth,josgarithmetic,greenestamps,mccravyedwin)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
If three men take 3 days to complete a piece of work, how many days will 2 men take to... (answered by reynard2007)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
It will take 24 men working 9 hours a day each to build a house in 45 days. Given that... (answered by lwsshak3)