Question 489777: Joshua can finish a certain job in 4 days while Kevin can finish the same job in 2 days. How long will it take them to finish the job it they work together?
Answer by stanbon(75887) (Show Source): You can put this solution on YOUR website!
Joshua can finish a certain job in 4 days while Kevin can finish the same job in 2 days. How long will it take them to finish the job it they work together?
----
Joshua rate = 1/4 job/day
---
Kevin rate = 1/2 job/day
---
Together rate = 1/x job/day
---------------------------------
Equation:
rate + rate = together rate
1/4 + 1/2 = 1/x
x + 2x = 4
3x = 4
x = 4/3 days = 1 1/3 days (time for them to do the job together)
================
Cheers,
Stan H.
================
RELATED QUESTIONS
A does a job in 6 days while B can do the same job in 4 days. how long will it take A and (answered by josgarithmetic)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
father can finish a certain job in 8 days while his daughter can finish the same job in... (answered by josmiceli)
oliver alone can finish a certain job in 6 days and karl alone can do the same in 4... (answered by richwmiller)
Danny can finish a job in 10 days. Together, Miguel and Danny can finish the same job in... (answered by rothauserc,ikleyn)
Kevin and Michael can finish a job in 9 3/5 days. Kevin can do the job himself in twelve... (answered by josgarithmetic)
It takes Victor 6 days more to paint a house than Roger. If they work together, they can... (answered by rothauserc,ikleyn)
A can finish a certain job in 10 days if B will help for 6 days. The same work can be... (answered by ankor@dixie-net.com)
A can finish a certain job in 12 days . A&B can finish same job in 8 days.how many day... (answered by nerdybill)