Question 481129: If 15 workers can paint 18 houses in 24 days, how many days will 40 workers take to paint 22 houses?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
If 15 workers can paint 18 houses in 24 days, how many days will 40 workers take to paint 22 houses?
--------------
# of days are inversely related to # of workers and directly related
to # of houses.
--------------
d = kh/w
---
Solve for "k" using "15 workers can paint 18 houses in 24 days"
24 = k*18/15
k = 15*24/18 = 15*(4/3) = 20
--------------
Equation:
d = 20h/w
---
Solve: How many days will 40 workers take to paint 22 houses?
d = 20*22/40
d = 11 days
===================
Cheers,
Stan H.
===================

RELATED QUESTIONS

If 15 workers can paint a certain number of houses in 24 days, how many days will 40... (answered by fractalier)
Five workers paint four houses in six days. Working at the same rate as these workers,... (answered by promotion analysis,ankor@dixie-net.com)
8 workers can paint a building in 24 days.How many days will 18 workers take to paint the (answered by Theo)
Six workers can paint 4 houses in 8 days. How many additional workers are needed if the... (answered by edjones)
8 workers can paint a building in 24 days . How many days will 18 workers take to paint... (answered by bdolan911)
Six workers can paint 4 houses in 8 days. ahow many additional workers are neededi if the (answered by ankor@dixie-net.com)
If 5 men can paint 26 houses within 3 days, how many houses can 15 men paint in 150... (answered by richwmiller)
Ten Men Can Paint 2 Houses in 8 Days. How Many Men Will He Required to Paint 15 Houses In (answered by stanbon)
if 4 painters can paint 2 houses in 3 days, how many painters would it take to paint 5... (answered by richwmiller)