SOLUTION: A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How long will it take for 3 boys and 6 girls to do the job?

Algebra.Com
Question 479212: A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How long will it take for 3 boys and 6 girls to do the job?
Answer by Edwin McCravy(20056)   (Show Source): You can put this solution on YOUR website!
A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How long will it take for 3 boys and 6 girls to do the job?
8 girls can do it in 5 days, so 1 girl can do it in 40 days.
So each girl's rate is 1 job per 40 days or  job/day

5 boys can do it in 6 days, so 1 boy can do it in 30 days.
So each boy's rate is 1 job per 30 days, or  job/day.

3 boy's combined rate is  or  jobs/day
6 girl's combined rate is  or  jobs/day.

Let x be the number of days for 3 boys and 6 girls to do the job.

Then in those x days, the boys do x of the job and the girls 
do x of the job.  That must add to 1 job so the equation is

                x + x = 1

Multiply through by 20

                 2x + 3x = 20

                      5x = 20

                       x = 4 days

Edwin

RELATED QUESTIONS

A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How (answered by emargo19)
A boys' club decides to build a cabin. The job can be done by 3 skilled workmen in 4 days (answered by stanbon)
three man can finish a painting job in 8 days. This job can be finished by 5 women in 6... (answered by ankor@dixie-net.com)
a girl can build a project on 12 days. a boy can build the same project in 8 days. if... (answered by Edwin McCravy)
20 men or 30 boys can do a certain job in 20 days. how long will it take 6 men and 15... (answered by ankor@dixie-net.com)
3 boys are working on a school project. Joseph and Bill can finish the prohectbin 10... (answered by josgarithmetic,greenestamps)
Suppose Carlo and Jordan can do the project together in 4 days. If Carlo can finish the... (answered by vleith)
Jonathan can complete a project in 15 days and Stephanie can do the same project in 45... (answered by richwmiller)
one man & 2 boys can do a piece of workin 12 days, which can also done by 3 men & 1 boy... (answered by stanbon)