SOLUTION: 6 people working 5 hours per day take 2 days to plant 500 shrubs. How many days would it take 4 people working 6 hours per day to plant 800 shrubs?

Algebra.Com
Question 479114: 6 people working 5 hours per day take 2 days to plant 500 shrubs. How many days would it take 4 people working 6 hours per day to plant 800 shrubs?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
6 people working 5 hours per day take 2 days to plant 500 shrubs.
Find the no. of man-hrs required to plant 500 shrubs
6 * 5 * 2 = 60 man hrs
then
= 12 man-hrs to plant 100 shrubs
:
How many days would it take 4 people working 6 hours per day to plant 800 shrubs?
Find no. of man-hrs to plant 800 shrubs
8 * 12 = 96 man-hrs to plant 800 shrubs
:
let d = no. of days to plant 800 shrubs
4 * 6 * d = 96
24d = 96
d =
d = 4 days to plant 800 shrubs with 4 men working 6 hrs a day

RELATED QUESTIONS

It takes 6 days to clean a house working 4 hours per day. How many days will it take to... (answered by Fombitz)
It takes 6 people 6 days to do a job. How many days would it take 2 people working at the (answered by josmiceli)
if 4 men can mow certain piece of land in 6 days ,working 10 hours a day, how many days... (answered by Alan3354,stanbon)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
10 men working for 5 hours a day for 6 days mow an area of 5 acres. If there are 8 men... (answered by josmiceli)
if 4 painters complete a painting job in 15 days working hours per day, how long would it (answered by ankor@dixie-net.com)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
(a).60 people working 8 hours a day takes 4 days to farm . How long will it take 20... (answered by ikleyn)