SOLUTION: A can do a piece of work in 16 days and B can do it in 20 days. These worked together for 5 days and then B leaves in how many days will finish the semaining work. (Ans.7)
Algebra.Com
Question 479078: A can do a piece of work in 16 days and B can do it in 20 days. These worked together for 5 days and then B leaves in how many days will finish the semaining work. (Ans.7)
Answer by robertb(5830) (Show Source): You can put this solution on YOUR website!
<==>
==>
==>
==> 5 + A = 12
==> A = 7 days for A to finish the remaining work.
RELATED QUESTIONS
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A can do a piece of work in 20 days which B can do it in 12 days. B worked at it for 9... (answered by mananth)
A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In... (answered by Edwin McCravy,AnlytcPhil,Edwin Parker)
A can do a piece of work in 24 days, B in 32 days and C in 64 days. all begin to do it... (answered by Jolliano)
A can do a piece of work in 30 days,and B can do the same work in 40 days,if both do... (answered by richwmiller)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)