SOLUTION: 4 men and 10 boys can solve a task in 18 days . how many days will require to solve the task by 12 men and 30 boys?

Algebra.Com
Question 469334: 4 men and 10 boys can solve a task in 18 days . how many days will require to solve the task by 12 men and 30 boys?
Answer by edjones(8007)   (Show Source): You can put this solution on YOUR website!
triple the workers divides the hours required by 3.
6 days Answer.
.
Ed

RELATED QUESTIONS

If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)
2 men can do the same amount of work that 3 boys can do. 4 men and 10 boys can do a piece (answered by josgarithmetic)
Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days... (answered by nshah11,hibiskus)
10 men or 18 boys can do a piece of work in 15 days, in how many days will 25 men and 15... (answered by Edwin McCravy)
if 4 men or 6 women can build a house in 56 days. how many days can 2 men and 5 women... (answered by josgarithmetic,MathTherapy)
20 men or 30 boys can do a certain job in 20 days. how long will it take 6 men and 15... (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
It takes Jose 12 days to complete a task. The same task would take Hans 24 days. After... (answered by mananth)