One man need 2hours to finished the job 2man need 5 hours.How long take both of them fibiahd the job
Answer by
Alan3354(69443)
(
Show Source
):
You can
put this solution on YOUR website!
In 1 hour, the 1st man can do 1/2 the job.
The 2nd man can do 1/5 of the job.
Together, they do 1/2 + 1/5 = 7/10 of the job in an hour.
--> 10/7 hours to do the job