SOLUTION: if it take 30 men to do a task in 16 days how many men would need 20 days for a task

Algebra.Com
Question 467210: if it take 30 men to do a task in 16 days how many men would need 20 days for a task
Found 2 solutions by Big Poop, ransz28:
Answer by Big Poop(157)   (Show Source): You can put this solution on YOUR website!

Answer by ransz28(1)   (Show Source): You can put this solution on YOUR website!
24
RELATED QUESTIONS

If 30 men need 16 days for a task, how many men would need 20... (answered by Tatiana_Stebko)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
4 men and 10 boys can solve a task in 18 days . how many days will require to solve the... (answered by edjones)
It takes Jose 12 days to complete a task. The same task would take Hans 24 days. After... (answered by mananth)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)
125 men completed a task in 120 days how many men will complete the same task in... (answered by josmiceli)
Suppose that 6 workers can complete a certain task in 10 days. If there are 20 (answered by josgarithmetic)
Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days... (answered by nshah11,hibiskus)