SOLUTION: if sam can do a certian job in 3 days while it takes fred 6 days to do the same job how long will it take them working together to complete the job?
Algebra.Com
Question 415493: if sam can do a certian job in 3 days while it takes fred 6 days to do the same job how long will it take them working together to complete the job?
Answer by solver91311(24713) (Show Source): You can put this solution on YOUR website!
If A can do a job in x time periods, then A can do
of the job in 1 time period. Likewise, if B can do the same job in y time periods, then B can do
of the job in 1 time period.
So, working together, they can do
of the job in 1 time period.
Therefore, they can do the whole job in:
time periods.
John

My calculator said it, I believe it, that settles it
RELATED QUESTIONS
If Sam can do a job in 4 days, Lisa can do the same job in 6 days, and Tom can do the job (answered by stanbon)
A does a job in 6 days while B can do the same job in 4 days. how long will it take A and (answered by josgarithmetic)
Alma can do the job in 6 days while Rachel can do the same. In 12 days. How long will it... (answered by Cromlix)
if Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 day how long (answered by Mathtut)
x does a job in 6 days. Y does the same job in 3 days. If they do the job together, how... (answered by checkley77,caet)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by chitra)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ankor@dixie-net.com)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ptaylor)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by Mathtut)