Question 414469: Ho long will it take 6 workers to complete a task, give that 7 workers can complete the same task in 12 days
Found 3 solutions by solver91311, Edwin McCravy, stanbon:
Answer by solver91311(24713)   (Show Source): You can put this solution on YOUR website!


If 7 workers can do the task in 12 days, then 1 worker should be able to complete the task in 7 times 12 days. Then 6 workers should be able to complete the task in (7 times 12) divided by 6 days.

John

My calculator said it, I believe it, that settles it
The Out Campaign: Scarlet Letter of Atheism


Answer by Edwin McCravy(20056)   (Show Source): You can put this solution on YOUR website!
Ho long will it take 6 workers to complete a task, give that 7 workers can complete the same task in 12 days

Since 7 workers can complete the task in 12 days, it would take
one worker 7 times that long, and 7x12 = 84, so it would take one
worker 84 days. It will take 6 workers only 1/6 as long as it would
take one worker, and 1/6 of 84 is 14.  So it will take 6 workers 
14 days to complete the task.

Edwin

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Ho long will it take 6 workers to complete a task, give that 7 workers can complete the same task in 12 days
-------
# of workers and time to complete the task are indirectly related.
t = k/# of men
---
Solve for "k" using "7 workers can complete the task in 12 days":
12 = k/7
k = 84
----
Equation:
t = 84/# of men
----
Solve "How long will it take 6 workers to complete the task?"
t = 84/6
time = 14 days
======================
Cheers,
Stan H.
===============

RELATED QUESTIONS

How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
how long will it take 18 workers to complete a task, given that it take 9 days for 8... (answered by boilpoil)
How long will it take4 workers to complete a task, given that it takes 6 days for 6... (answered by josmiceli)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
Suppose that 5 workers can complete a certain task in 12 days. If there are 15 workers,... (answered by ankor@dixie-net.com)
Suppose that 6 workers can complete a certain task in 10 days. If there are 20 (answered by josgarithmetic)
If 20 workers can complete a task in 12 hrs, how long will it take 30... (answered by josgarithmetic)
How long will it take 20 machines to complete a task, given that it takes 12 days for 5... (answered by rfer)