SOLUTION: Marissa can arrange the card catalog of the library in 8 days. The assistant take 12 days to do it. If they work together, what part of the card catalog is arranged after 4 days?

Algebra.Com
Question 412931: Marissa can arrange the card catalog of the library in 8 days. The assistant take 12 days to do it. If they work together, what part of the card catalog is arranged after 4 days?

Answer by mananth(16946)   (Show Source): You can put this solution on YOUR website!
Marissa ----- 8 days
so she does 1/8 of the job in 1 day
..
assistant ----- 12 days
she does 1/12 of the job in 1 day.
...
together they do 1/8 + 1/12 of the job in 1 day
=5/24 of the job in 1 day.
so in 4 days they will do
4*5/24 of the job
= 5/6 of the job in 4 days.

RELATED QUESTIONS

Lorna can arranged the catalog card in the library in 8 days.Her assistant takes 12 days... (answered by josgarithmetic,greenestamps)
alma can do a job in 6 days. rachel can do job in 12 days. how long it will take if they... (answered by nihar*2013)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
If Jon can paint a house in 5 days and James can do same in 8 days, how many days will it (answered by Alan3354)
Alma can do the job in 6 days while Rachel can do the same. In 12 days. How long will it... (answered by Cromlix)
Mrs. Hensen cataloged a group of incoming library books in 8 hours. Mr. Taylor can... (answered by josmiceli)
If A completes a particular work in 4 days and B the same work in 12 days. How many days... (answered by richwmiller)
John can complete a task in 18 days while Peter can complete it in 12 days. How many days (answered by math_helper)
if berna can paint the house in 12 days and dette can paint the house in 16 days, how... (answered by Cromlix)