SOLUTION: If it takes 3 man 4 days to lay 400 feet of pipe, how many men will it take to lay 2400 feet of pipe in 2 days?

Algebra.Com
Question 404174: If it takes 3 man 4 days to lay 400 feet of pipe, how many men will it take to lay 2400 feet of pipe in 2 days?
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
3 men work 3 times as fast as 1 man.
If it takes 3 man 4 days to lay 400 feet of pipe
Then it takes 1 man 12 days to lay 400 ft of pipe (3 times as long)
To lay 6 times as much pipe in the same time , it takes 6 times as many men
Thus it will take 6 men 12 days to lay 2400 ft of pipe
It will take 6 times as many men to lay 2400 ft of pipe in 1/6 of that time
Thus it will take 36 men 2 days to lay 2400 ft of pipe (answer)
------------------------------------------

RELATED QUESTIONS

If 3 hens lay 4 eggs in 5 days, how many days will it take a dozen hens to lay 8 dozen... (answered by stanbon)
If 20 men can lay 36 m of pipe in 8 hours. How long would 25 men take to lay the next 54... (answered by josgarithmetic)
It takes j 6 hours to lay 100 square feet of tile. It takes k 5 hours to lay 100 square... (answered by ikleyn,Boreal)
if four hens lay 9 eggs in 7 days, how many days will it take four dozen hens to lay 27... (answered by stanbon)
if four hens lay 9 eggs in 7 days, how many days will it take four dozen hens to lay 27... (answered by stanbon)
A carpet layer can put down 400 square feet of carpeting in 2.5 hours. How many hours... (answered by ikleyn,Alan3354)
A carpet layer can put down 400 square feet of carpeting in 2.5 hours. How many hours... (answered by ikleyn)
It takes 4 workers 9 days to lay a stretch of road. How long does it take 6 workers to... (answered by josmiceli)
it takes 21 days for 21 chickens to lay 21 eggs, how many days will take 14 chickens to... (answered by Edwin McCravy)