SOLUTION: If it takes 4 days for 6 people to finish a job, than how many days does it take 8 people to finish the same job?

Algebra.Com
Question 398502: If it takes 4 days for 6 people to finish a job, than how many days does it take 8 people to finish the same job?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
If it takes 4 days for 6 people to finish a job, than how many days does it take 8 people to finish the same job?
----
# of days is inversely related to # of people on the job.
-------
d = k/p
---
Solve for "k" using "it takes 4 days for 6 people to finish a job".
4 = k/6
k = 24
---
Equation for this problem:
d = 24/p
-----
Than how many days does it take 8 people to finish the same job?
d = 24/8
# of days = 3
====================
Cheers,
Stan H.

RELATED QUESTIONS

If 3 people finish a given job in 8 days,how many days will it take for 2 people to... (answered by ptaylor)
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
It takes Victor 6 days more to paint a house than Roger. If they work together, they can... (answered by rothauserc,ikleyn)
10 people finish a job in 16 hours, how many hours would it take for 8 people to finish... (answered by hovuquocan1997,edjones)
If 4 people take 6 days to do a painting job, how many days will it take 3 people to do... (answered by josmiceli,Edwin McCravy)
It takes 12 people 1 day to finish 1 job, how long would it take 8 people to finish the... (answered by Fombitz)
Danny can finish a job in 10 days. Together, Miguel and Danny can finish the same job in... (answered by rothauserc,ikleyn)
It takes 6 people 6 days to do a job. How many days would it take 2 people working at the (answered by josmiceli)
If it takes a crew 9 days to do 80% of the job, how many more days will it take to finish (answered by josmiceli)